U.S. Multifamily Starts Drop 25.9% as September Construction Costs Climb
Permits rise while starts retreat
Apartment development remains constrained by a widening gap between projects that are permitted and those developers can finance. September’s 25.9% annual drop in multifamily starts points to that hesitation, even as permits rose and rent growth showed some improvement. The split matters: approvals show that projects have cleared an early step, while starts indicate that construction has actually begun. A larger pool of permitted projects can therefore coexist with a subdued building pace.
Permits rise while starts retreat
Buildings with five or more units recorded a seasonally adjusted annual starts rate of 349,000 in September, down 7.2% from August and 25.9% from a year earlier, according to HUD and the U.S. Census Bureau. Completions also stayed below last year’s pace: the September rate of 339,000 was up 14.9% month over month but down 20.4% year over year. These measures describe different stages of construction, so a monthly increase in completions doesn’t erase the annual decline, and it doesn’t establish that new projects are accelerating.
Permits for multifamily buildings moved in the opposite direction. The seasonally adjusted rate reached 503,000, an increase of 5.9% from August and 1% from September 2025. That rise suggests more projects had permission to proceed, but permission is only one part of the development process. Developers still need to decide whether expected revenue can support the cost of building and financing a project. The approvals indicate a pipeline of potential projects, but they don’t guarantee construction will begin.
“We've got planned properties that are ready to go. We could start tomorrow, but it's a question of, is the money there,” Leaselock Chief Economist Greg Willett told Multifamily Dive. He said improving rent growth could encourage developers to break ground, while interest rates continue to weigh against doing so. “So, are these projects going to go or not? I'm not sure.” His uncertainty captures the central tension: a project can be ready in practical terms and still fail the financial test. A permit alone can’t settle that question.
Here's the thing: stronger rent growth may improve a project's prospects, but the figures provided don’t show how much improvement would be enough to offset financing costs. That leaves the permit increase open to interpretation. It may represent a pool of projects that will eventually proceed, or plans that remain on hold while developers assess whether the economics work.
Housing starts weaken nationally
All privately owned housing starts fell to a seasonally adjusted annual rate of 1.2 million, 5.2% below August’s revised figure and 7.4% below September 2025. Single-family starts reached 859,000, down 4.6% from August but 2.6% above the year-earlier rate. The contrast suggests the annual contraction was steeper in multifamily than in single-family construction. It also cautions against treating the national decline as a uniform pullback across every type of housing.
For readers tracking apartment supply, the multifamily figures are the more direct signal: fewer starts mean fewer projects have moved into construction during the measured period. Completions offer a separate view of homes reaching the end of that process, but September’s monthly gain doesn’t reverse the year-over-year drop. The figures describe activity, not the reasons behind each individual project's timing. Financing and rent expectations help explain the hesitation cited by Willett, while the construction cost pressures described below add another constraint.
The South separates from other regions
The South was the only region where total housing starts increased year over year, rising 11% in September. Single-family starts there climbed 8.8%. Elsewhere, overall starts fell 30.9% in the Northeast, 25.4% in the West and 19.4% in the Midwest. In each of those regions, single-family activity held up better than the total that includes apartments.
That regional split is a useful reminder that national totals can conceal very different local patterns. The South’s increase stands apart from the declines in the other regions, but the figures here don’t explain what drove that difference or show whether it will persist. Nor should the regional totals be read as a direct measure of apartment construction alone: they cover total starts, with single-family figures reported separately. For developers and contractors, local conditions still shape whether a permitted project can move ahead. A national increase or decline can’t answer that on its own.
Material costs add pressure
Development economics face another headwind from construction inputs. Prices rose 2.2% month over month in September and 11.2% year over year, the largest annual increase in nearly four years, according to an Associated Builders and Contractors analysis of federal Producer Price Index data. ABC attributed much of the latest increase to higher fuel costs linked to the Iran war and tariffs on key building materials, with petroleum products and metals among the categories posting the largest increases.
Rising input prices matter because they add to the cost of delivering a project at a time when developers are already weighing financing against expected rent growth. The data don’t quantify how much these increases add to any one apartment development, and the effect can vary by project. Still, higher prices for fuel and metals can put pressure on budgets and make cost estimates harder to hold as work proceeds. That adds another reason a developer might delay a start while testing whether a project still makes financial sense.
Supply timing is tightening too. Associated General Contractors of America Chief Economist Ken Simonson said lead times for key steel components had lengthened, making it harder for contractors to keep projects on schedule. A delayed component can complicate planning and extend the period before a building is completed; the source doesn’t say how often that’s happening or how much time projects are losing. The practical issue is that cost and timing pressures can reinforce one another. And this is the part most people overlook: a permitted project can remain stalled even when its plans are ready, if the financing and construction conditions don’t line up. A waiting pipeline, not yet a wave of new supply.
What the gap means for the pipeline
The September figures point to a multifamily sector with approvals in place but fewer projects starting construction than a year earlier. That gap is more significant than it looks because permits are often treated as a preview of future building, when they’re better understood as a measure of potential activity. What this means for you, if you're working in this space, is that the permit count alone won’t tell you how much construction is actually underway.
That said, the data don’t establish whether the September slowdown will continue. Rent growth could encourage some developers to proceed, while interest rates, material prices and longer lead times remain obstacles described in the source. The next useful signal will be whether permitted projects begin turning into starts, alongside how completions compare with the prior year. Until then, the pipeline is evidence of plans, not proof that those plans will become apartments.